Herman Miller (LA Showroom) 3641 Holdrege Avenue Los Angeles, CA
Start Date: 03/09
Completion Date: 08/09
General Contract: Howard Building Corporation
Architect: Thomas, Ventulett, Stainback & Associates, Inc.
Engineer: Arc Engineering
 
Bridge Publications 5600 E. Olympic Blvd., Commerce, CA
Start Date: 02/09
Completion Date: 06/09
General Contract: Turelk, Inc.
Architect: Kamus + Keller Architects
Engineer: A & F Consulting Engineers
 
CCH 20101 Hamilton Ave. Torrance CA
Start Date: 05/08
Completion Date: 11/08
General Contract: Clune Construction
Architect: Wirt Design Group
Engineer: Boone Electric, Inc.
 
Deluxe Media 3rd Floor Improvements 2350 Empire Avenue 3rd Floor Burbank, CA
Start Date: 12/07
Completion Date: 04/08
General Contract: Warner Constructors
Architect: Wirt Design Group
Engineer: Boone Electric, Inc.
 
(11) Wachovia Banks Southern California
Start Date: 12/06
Completion Date: 11/08
General Contract: NK David Constructors
Architect: Callison Architects
Engineer: Dale Schnakel
 
USC Dr. Hutchins Mezzanine Lab Project "E" 3616 Trousdale Parkway Los Angeles, CA
Start Date: 08/07
Completion Date: 10/08
General Contract: Clune Construction
Architect: Lundstrom & Assoc.
Engineer: Kocher, Schirra & Goharizi
 
Blue Shield of America 100 N. Sepulveda 19th and 20th Floors El Segundo, CA
Start Date: 3/07
Completion Date: 07/07
General Contract: Warner Constructors
Architect: ISI
Engineer: ARC Engineering
 
Wella Sebastian (De Soto Ave. & Variel Ave.) 6109 De Soto Ave., & 6110 Variel Ave., Woodland Hills, CA
Start Date: 07/07
Completion Date: 01/08
General Contract: Howard Building Corporation
Architect: Interior Architects
Engineer: Boone Electric, Inc.
 
The Jonathan Club Emergency Lighting Retrofit 545 S. Figueroa St Los Angeles, CA
Start Date: 08/07
Completion Date: 12/07
General Contract: None
Architect: None
Engineer: Syska & Hennessey
 